Paint/Coatings Manufacturing Facility Expansion Covington, GA
September 16, 2014
Century completed a 30,000 square feet expansion for one of the largest paint and coatings company in the world. The project consisted of adding two new process manufacturing lines to an existing manufacturing facility. As the General Contractor, Century self-performed more than 50% of the project work activities.
Major areas of work included:
- Sitework
- Concrete
- Masonry
- Structural Steel
- Equipment Platform and Support Steel
- Equipment Installation
- Utility and Process Piping
- HVAC and Process Ductwork
- Insulation
- Architectural Finishes
- Electrical and Controls